Advance notice of Network Rail re-signalling works in February and March

Feb 6, 2024 | Parish Council News

Email received 1st February 2024

“We previously wrote to you about the major signalling works in Devon and Cornwall to improve safety and reliability and offer the potential to add more trains for the Mid Cornwall Metro scheme.
This work will see the replacement of older-style signals and equipment with brand-new, digital technology. For this work to be done, the Cornish Main Line will be temporarily closed in phases between Tuesday 27 February and Sunday 10 March with buses replacing trains on various routes in the county. We’ll also have ticket acceptance in place on certain local bus routes.
In Devon, the line between Totnes and Plymouth will be closed from Saturday 16 March to Friday 22 March. This will extend to Exeter St Davids over the weekend of 17/18 March as well as after 2140 on most weeknights. Rail replacement road transport will operate between affected stations. We will also run non-stop buses between Tiverton Parkway and Plymouth throughout the week.
The Night Riviera sleeper service will continue to be affected during both sets of work – more information is available on our dedicated webpage at https://www.gwr.com/travelling-with-us/night-riviera-sleeper.
Online journey planners have been updated and we’ll also be letting customers know through onboard and station announcements, station posters, and traditional and social media.
Any help you can give to remind your networks of the works would be much appreciated, and if there’s anything we can do to help please get in touch.
Best wishes
Tom & Heledd

Thomas Lydon | Public Affairs Manager | Great Western Railway

Heledd Iolo, Public Affairs Manager, Network Rail Western”

0 Comments

Submit a Comment

Your email address will not be published. Required fields are marked *

Related Articles:

Midges  & Millbrook Lake Flushing

Midges & Millbrook Lake Flushing

Printable version At the Annual Parish meeting this year there was a request made not to flush the lake during the bird nesting season - The Environmental Agencies confirmed that the lake is flushed regularly to reduce the numbers of midges, which coincides with the...

MPC Annual Governance and Accountability Return 2025-26

MPC Annual Governance and Accountability Return 2025-26

Annual Internal Audit Report 2025/26 Annual Governance Statement 2025/26 Accounting Statements 2025/26 Explanation of Variance Report 2025/26 Annual Bank reconciliation 2025/2026 BDO Confirmation there are no conflicts of interest Notice of Public Rights and...